G:\Design & Construction Services\Projects\2011\11-201\Project Manual\24_Special Conditions_042909 REV.doc
SPECIAL CONDITIONS
1. TIME OF COMPLETION
Work in this contract shall be substantially completed by August 1, 2012, assuming the Notice to
Proceed is issued as stated below.
2.
NOTICE TO PROCEED
The intended Notice to Proceed is May 1, 2012. In the event that the NTP is later than the stated date,
the date of Substantial Completion shall be increased the same number of days the NTP is issued
beyond the above date.
3.
LIQUIDATED DAMAGES
See Section 49 of the ABC Form C-8, General Conditions.
4. PROJECT SIGN
:
A project sign is not required for this project.
5.
RAIN DAY CLASS:
For the purpose of granting time extensions due to rain, this project is considered a Class V project.
6.
BUILDER’S RISK INSURANCE:
To be provided by General Contractor.
7.
COORDINATION WITH ADJACENT PROJECT:
General Contractor and its subcontractors shall coordinate with the work being performed
simultaneously with AU Project 11-221, Native American Collection, in the same space. Contractors
shall determine coordinated scope and schedule prior to construction and shall present the
coordination plan to the AU Project Manager.
8.
GYPSUM BOARD JOINT COMPOUND PRECAUTIONS
It has been determined that the joint compound used in some of the gypsum board wall assemblies
contains trace amounts of less than 1% asbestos. Although this amount is not considered Asbestos
Containing Material (ACM) per EPA and OSHA thresholds, the General Contractor is required per
OSHA to protect workers from any airborne asbestos exposure.
9.
PROJECT SUBMITTALS / SCHEDULE:
All submittals will be required for this project and a detailed schedule including submittal issue and
return dates will need to be prepared and delivered to the AU Project Manager prior to start of
construction. The schedule will need to be updated weekly and will be reviewed at weekly on site
meetings with the AU PM.